Integrated Annual Report of LOTOS Capital Group 2016

13. Property, plant and equipment and intangible assets

Download XLS(122 KB)

Note Dec 31 2016 Dec 31 2015
Non-current assets of the downstream segment 13.1 8,431,723 8,019,780
Property, plant and equipment 13.1.1 8,261,718 7,845,051
Intangible assets, including: 170,005 174,729
     Goodwill 13.1.2 45,562 45,562
     Other intangible assets 13.1.3 124,443 129,167
Non-current assets of the upstream segment 13.2 2,871,791 3,213,061
Property, plant and equipment 2,389,960 2,723,371
Intangible assets, including: 481,831 489,690
     Goodwill 1,126 1,126
     Other intangible assets 480,705 488,564
Total property, plant and equipment and intangible assets   11,303,514 11,232,841
including:
     Property, plant and equipment 10,651,678 10,568,422
     Intangible assets 651,836 664,419

13.1 Non-current assets of the downstream segment

13.1.1 Property, plant and equipment of the downstream segment
Land Buildings, structures Plant and equipment Vehicles, other Property, plant and equipment under construction Total
Gross carrying amount
Jan 1 2016
510,178 4,474,591 5,556,358 620,198 395,883 11,557,208
Purchase - - - 20,431 903,139 923,570 (1)
Transfer from property, plant and equipment under construction 12,771 93,045 53,376 49,485 (208,677) -
Borrowing costs - - - - 4,775 4,775
Reclassification to non-current assets (or disposal group) held for sale - - - (2,095) - (2,095)
Disposal (5,600) (5,696) (15,298) (12,072) (378) (39,044)
Other - 412 (1,145) (8,709) (2,748) (12,190)
Gross carrying amount
Dec 31 2016
517,349 4,562,352 5,593,291 667,238 1,091,994 12,432,224
Accumulated depreciation
Jan 1 2016
14,796 1,436,898 1,926,322 266,690 - 3,644,706
Depreciation 1,733 174,853 236,117 61,612 - 474,315
Reclassification to non-current assets (or disposal group) held for sale - - - (1,363) - (1,363)
Disposal (448) (2,623) (14,446) (9,127) - (26,644)
Other - 224 575 1,624 - 2,423
Accumulated depreciation
Dec 31 2016
16,081 1,609,352 2,148,568 319,436 - 4,093,437
Impairment losses
Jan 1 2016
1,158 44,411 5,731 2,576 13,575 67,451
Recognised 349 11,307 919 1,965 - 14,540
Used/Reversed (56) (4,254) (255) (357) - (4,922)
Impairment losses
Dec 31 2016
1,451 51,464 6,395 4,184 13,575 77,069
             
Net carrying amount
Dec 31 2016
499,817 2,901,536 3,438,328 343,618 1,078,419 8,261,718

(1) Capital expenditure included chiefly expenditure on the construction of a delayed coking unit with auxiliary infrastructure of the EFRA Project (PLN 672,291 thousand), expansion of the service station chain (PLN 105,503 thousand), and construction of the hydrogen recovery unit (PLN 55,632 thousand).

Land Buildings, structures Plant and equipment Vehicles, other Property, plant and equipment under construction Total
Gross carrying amount
Jan 1 2015
482,078 4,390,585 5,527,810 526,882 171,339 11,098,694
Purchase - - - 4,752 432,422 437,174 (2)
Transfer from property, plant and equipment under construction 29,645 91,335 50,834 34,139 (205,953) -
Borrowing costs - - - - 1,331 1,331
Disposal (1,910) (9,191) (21,306) (36,832) (1) (303) (69,542)
Finance lease - - 24 97,344 - 97,368
Other 365 1,862 (1,004) (6,087) (2,953) (7,817)
Gross carrying amount
Dec 31 2015
510,178 4,474,591 5,556,358 620,198 395,883 11,557,208
Accumulated depreciation
Jan 1 2015
13,176 1,270,085 1,710,170 265,150 - 3,258,581
Depreciation 1,620 172,515 235,272 44,142 - 453,549
Disposal - (6,709) (19,668) (36,293) (1) - (62,670)
Finance lease - - - (7,344) - (7,344)
Other - 1,007 548 1,035 - 2,590
Accumulated depreciation
Dec 31 2015
14,796 1,436,898 1,926,322 266,690 - 3,644,706
Impairment losses
Jan 1 2015
1,067 37,466 5,176 1,863 13,601 59,173
Recognised - 9,991 721 754 15 11,481
Used/Reversed - (3,951) (166) (41) (41) (4,199)
Other 91 905 - - - 996
Impairment losses
Dec 31 2015
1,158 44,411 5,731 2,576 13,575 67,451
             
Net carrying amount
Dec 31 2015
494,224 2,993,282 3,624,305 350,932 382,308 7,845,051

(1) Including retirement of worn-out spare parts in the amount of PLN 19,513 thousand
(2) Capital expenditure included chiefly expenditure on the construction of a delayed coking unit with auxiliary infrastructure of the EFRA Project (PLN 191,488 thousand), expansion of the service station chain (PLN 130,230 thousand), and construction of the hydrogen recovery unit (PLN 44,434 thousand).

Property, plant and equipment of the downstream segment include chiefly Group’s assets related to refining and marketing activities, such as the refinery infrastructure, service station network, rolling stock, storage depots, and property on which the production plants, production units, and office buildings are located.

Impairment losses on service stations

In 2016, LOTOS Paliwa Sp. z o.o. recognised an impairment loss on service station assets totalling PLN 13,122 thousand (2015: PLN 10,288 thousand); see Note 9.4. The recoverable amount of property, plant and equipment related to the service station network was determined based on the value in use of each station, calculated with the discounted cash flow method. Future cash flows were calculated based on five-year cash-flow projections, prepared using budget projections for 2017 (in 2015: for 2016) and the cash inflow and outflow plan for subsequent years, based on the development strategy until 2020. The residual value for the discounted cash flows was calculated using the growing perpetuity formula. LOTOS Paliwa Sp. z o.o.’s net weighted average cost of capital (WACC) was assumed at 8.22% (2015: 7.3%), based on the company’s financing structure. 

Calculation of the value in use of cash-generating units is most sensitive to the following variables:

  • gross margin, which depends on average values of unit margins in the period preceding the budget period (a 4.5% average year-on-year margin increase was assumed),
  • discount rates, reflecting risks typical to the cash-generating unit (the median for five-year PLN-denominated notes quoted by Reuters in November 2015 was adopted),
  • volumes based on fuel consumption growth rate (an 11% increase was assumed),
  • market share in the budget period (a stable market share was assumed),
  • growth rate used to extrapolate cash-flow projections beyond the budget period, based on a quantitative forecast of the fuel consumption growth rate in Poland in 2014−2020, prepared using POPiHN, GUS, NBP and JBC reports (for gasolines), and based on GDP market consensus. In the case of diesel oil, the data included also the market consensus on GDP and its constituent elements sourced from IBNGR, BZWBK, MILLENIUM, NBP, MG, EBOIR, WFM, OECD, KE, and ERSTE GROUP.
13.1.2 Goodwill of the downstream segment

Goodwill is allocated to cash-generating units, as presented in the table below:

Dec 31 2016 Dec 31 2015
Goodwill arising on the acquisition of an organised part of business by LOTOS Paliwa Sp. z o.o.:
- wholesale of LPG 10,009 10,009
- service stations networks (ESSO, Slovnaft Polska) 33,691 33,691
Total 43,700 43,700
Goodwill arising on acquisition of other entities 1,862 1,862
Total goodwill 45,562 45,562

As at December 31st 2016 and December 31st 2015, impairment tests of individual cash-generating units to which goodwill was allocated did not reveal any impairment indicators.

The Group determines the recoverable amount of cash-generating units based on their respective values in use, calculated on the basis of a five-year cash flow projection. The residual value for the discounted cash flows was calculated using the growing perpetuity formula. The discount rate adopted for the calculation reflects net WACC of 8.22% (2015: 7.3%). 

The most material factors affecting the estimated values in use of cash-generating units were: gross margin, discount rate, volumes forecast, projected market shares in the budget period and estimated growth rate beyond the forecast period.

The Group believes that no reasonably probable change in the key parameters identified above would result in goodwill impairment.

13.1.3 Other intangible assets of the downstream segment
Patents, trademarks and licences Other Intangible assets under development  Total
Gross carrying amount
Jan 1 2016
197,907 36,297 18,855 253,059
Purchase - 198 6,962 7,160
Transfer from intangible assets under development 7,679 895 (8,574) -
Borrowing costs - - 65 65
Other (240) (306) - (546)
Gross carrying amount
Dec 31 2016
205,346 37,084 17,308 259,738
Accumulated amortisation
Jan 1 2016
100,883 13,944 - 114,827
Amortisation 10,428 1,172 - 11,600
Other (56) (141) - (197)
Accumulated amortisation
Dec 31 2016
111,255 14,975 - 126,230
Impairment losses
Jan 1 2016
7 25 9,033 9,065
Recognised - - - -
Used/Reversed - - - -
Impairment losses
Dec 31 2016
7 25 9,033 9,065
Net carrying amount
Dec 31 2016
94,084 22,084 8,275 124,443
Gross carrying amount
Jan 1 2015
192,477 43,953 12,804 249,234
Purchase - 84 12,145 12,229
Transfer from intangible assets under development 5,721 393 (6,114) -
Borrowing costs - - 52 52
Disposal (154) (7,768) (1) (30) (7,952)
Other (137) (365) (2) (504)
Gross carrying amount
Dec 31 2015
197,907 36,297 18,855 253,059
Accumulated amortisation
Jan 1 2015
91,219 13,304 - 104,523
Amortisation 9,816 1,237 - 11,053
Disposal (152) (606) - (758)
Other - 9 - 9
Accumulated amortisation
Dec 31 2015
100,883 13,944 - 114,827
Impairment losses
Jan 1 2015
7 8 9,033 9,048
Recognised - 17 - 17
Used/Reversed - - - -
Impairment losses
Dec 31 2015
7 25 9,033 9,065
Net carrying amount
Dec 31 2015
97,017 22,328 9,822 129,167

(1) Including retirement of CO2 emission allowances of PLN 7,163 thousand, used for own needs.

Intangible assets of the downstream segment include licences relating to technological processes, including licences for technologies used in the refinery, licences for fuel production, storage and trading, software licences, patents, trademarks and acquired CO2 emission allowances.

13.2 Non-current assets of the upstream segment

Note Dec 31 2016 Dec 31 2015
Exploration and evaluation assets 13.2.1 396,670 462,126
Property, plant and equipment 55,624 118,759
Intangible assets 341,046 343,367
Development and production assets 13.2.2 2,098,270 2,316,381
Property, plant and equipment 1,966,931 2,182,903
Intangible assets 131,339 133,478
Other non-current assets 13.2.3 376,851 434,554
Property, plant and equipment 367,405 421,709
Intangible assets 9,446 12,845
Total non-current assets of the upstream segment   2,871,791 3,213,061
including:
     Property, plant and equipment 2,389,960 2,723,371
     Intangible assets 481,831 489,690
13.2.1 Exploration and evaluation assets
    Note Property, plant and equipment classified as exploration and evaluation assets Intangible assets classified as exploration and evaluation assets   Total 
Poland Poland Norway Lithuania
Gross carrying amount
Jan 1 2016
  167,756 9,878 467,240 10,211 655,085
Purchase 1,692 361 51,951 (2) - 54,004
Exchange differences on translating foreign operations - - 43,627 389 44,016
Expenditure written off due to project discontinuation 9.4 (1,904) (1) (940) (1) (133,063) (3) - (135,907)
Gross carrying amount
Dec 31 2016
167,544 9,299 429,755 10,600 617,198
Accumulated depreciation and amortisation
Jan 1 2016
- 8,046 - - 8,046
Depreciation and amortisation - 1,627 - - 1,627
Expenditure written off due to project discontinuation 9.4 - (705) (1) - - (705)
Accumulated depreciation and amortisation
Dec 31 2016
  - 8,968 - - 8,968
Impairment losses
Jan 1 2016
  48,997 235 125,470 10,211 184,913
Recognised 9.4 64,827 (1) - 73,364 (4) - 138,191
Exchange differences on translating foreign operations - - 10,942 389 11,331
Used/Reversed 9.4 (1,904) (1) (235) (1) (120,736) (3) - (122,875)
Impairment losses
Dec 31 2016
  111,920 - 89,040 10,600 211,560
Net carrying amount
Dec 31 2016
  55,624 331 340,715 - 396,670

(1) Expenditure on exploration and evaluation activities related to the Słupsk area (decision to abandon the project) and the Gaz Południe area (a PLN 64,785 thousand write-off of expenditure on seismic surveys).
(2) Including expenditure on Sleipner assets (PLN 18,731 thousand ) and Heimdal assets (PLN 31,206 thousand ).
(3) Capitalised expenditures related to PL643 and PL655 licences (effect on the Group’s profit/(loss): PLN 12,327 thousand).
(4) Including the Utgard (formerly Alfa Sentral) field assets of PLN 67,615 thousand and PL797 licence of PLN 5,749 thousand.

    Note Property, plant and equipment classified as exploration and evaluation assets Intangible assets classified as exploration and evaluation assets   Total 
Poland Poland Norway Lithuania
Gross carrying amount
Jan 1 2015
  91,930 13,012 314,806 10,213 429,961
Purchase 27,372 15 8,100 - 35,487
Acquisition of Sleipner assets - - 188,471 (4) - 188,471
Exchange differences on translating foreign operations - - (29,291) (2) (29,293)
Reclassification to exploration and evaluation assets 60,577 (1) - - - 60,577
Expenditure written off due to project discontinuation 9.4 (12,123) (2) (3,149) (2) (14,846) (5) - (30,118)
Gross carrying amount
Dec 31 2015
  167,756 9,878 467,240 10,211 655,085
Accumulated depreciation and amortisation
Jan 1 2015
  - 7,277 - - 7,277
Depreciation and amortisation - 3,663 - - 3,663
Expenditure written off due to project discontinuation 9.4 - (2,894) (2) - - (2,894)
Accumulated depreciation and amortisation
Dec 31 2015
  - 8,046 - - 8,046
Impairment losses
Jan 1 2015
  47,161 - 134,078 - 181,239
Recognised 9.4 1,836 (3) 235 (3) - 10,027 (6) 12,098
Exchange differences on translating foreign operations - - (8,608) 184 (8,424)
Used/Reversed - - - - -
Impairment losses
Dec 31 2015
  48,997 235 125,470 10,211 184,913
             
Net carrying amount
Dec 31 2015
  118,759 1,597 341,770 - 462,126

(1) Related to operations on the Gaz Południe, Gotlandia, Łeba and Rozewie licence areas, which will be continued in 2016 in line with the upstream segment management’s decision. Applications were filed to convert the Łeba and Rozewie licences into combined oil and gas exploration, appraisal and production licences.
(2) Expenditure on exploration and evaluation activities related to the Sambia E field (effect on the Group’s profit/(loss): PLN 12,378 thousand).
(3) Słupsk area assets (effect on the Group’s profit/(loss): PLN 2,071 thousand).
(4) Utgard (formerly Alfa Sentral) and PL046 licences forming part of the acquired Sleipner assets in Norway (for more information on the transaction, see Note 13.1.3. to the Consolidated financial statements for 2015 ).
(5) Expenditure related to Heimdal assets − Fulla (PL362 and PL035B) and PL503 licence.
(6) Expenditure on seismic surveys.

Property, plant and equipment are classified as exploration and evaluation assets until the technical feasibility and commercial viability of extracting the discovered resources are demonstrated.

Impairment of assets of the Sleipner gas field in Norway

As at December 31st 2016, the Group tested the Utgard (previously Alfa Sentral) field at a pre-development stage for impairment. The test was performed based on the following assumptions, equivalent to those adopted for development and production assets:

  • the cash flow projection period was assumed to equal the asset’s planned life, 
  • the discount rate was assumed to equal the weighted average cost of capital, and was calculated at 7.63% after taxation with the 78% marginal tax rate (applicable in Norway), 
  • production and sales volumes, capital expenditure, operating expenses and field decommissioning costs were assumed as projected by the field operators.

The following price assumptions were adopted: 

- for crude oil in USD/bbl (per barrel):

  • 2017–2019 – prices in line with the price assumptions for the available market scenarios, 
  • 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation, 

- for natural gas in p/th (pence/thermal units):

  • 2017–2019 − prices in line with the price assumptions for the available market scenarios, and in 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation.

The USD/NOK exchange rate used for the purposes of the impairment test is a cross rate calculated based on forward curves for the EUR/USD and EUR/NOK currency pairs.

The measurement of the recoverable amount showed the necessity to recognise an impairment loss on those assets in the amount of PLN 67,615 thousand (NOK 143,100 thousand), see Note 9.4.

Due to significant market volatility, in particular with respect to oil and gas prices, the adopted assumptions may be subject to justifiable changes, and such changes may necessitate a revision of the carrying amounts of the Utgard field’s assets in the future. To determine the effect of key factors on the test results, the Group carried out an analysis of sensitivity to a -15%/+15% change in oil and gas price, -15%/+15% change in production volumes, and -15%/+15% change in the USD/NOK exchange rate. The table below presents the estimated changes in impairment losses following changes in the key assumptions:

Factor Change Impact on impairment losses PLN '000 
Crude oil and gas prices +/- 15% 49,618 - 47,498
Production volume +/- 15% 38,292 - 38,291
USD/NOK exchange rate +/- 15% 41,242 - 41,240
Discount rate +/- 0,5 pp - 4,914 5,052
13.2.2 Development and production assets
    Note Development assets   Production assets    Total
Poland Norway Total Poland Norway Lithuania Total
Gross carrying amount
Jan 1 2016
  - 1,452,412 1,452,412 1,384,677 1,497,203 636,138 3,518,018 4,970,430
Purchase - 12,026 (1) 12,026 213,183 (2) 46,259 (5) 78 259,520 271,546
Exchange differences on translating foreign operations - 127,705 127,705 - 146,438 24,252 170,690 298,395
Estimated costs of decommissioning of oil and gas extraction facilities - - - (2,921) (87,911) (389) (91,221) (91,221)
Reclassification to production assets - - - 58,549 (3) - - 58,549 58,549
Expenditure written off due to project discontinuation - - - (3,257) (4) - - (3,257) (3,257)
Other - - - 215 1,383 (321) 1,277 1,277
Gross carrying amount
Dec 31 2016
  - 1,592,143 1,592,143 1,650,446 1,603,372 659,758 3,913,576 5,505,719
Accumulated depreciation and amortisation
Jan 1 2016
  - - - 398,384 310,265 258,063 966,712 966,712
Depreciation and amortisation - - - 38,806 471,819 25,061 535,686 535,686
Exchange differences on translating foreign operations - - - - 44,877 10,113 54,990 54,990
Reclassification to production assets - - - 27,061 (3) - - 27,061 27,061
Expenditure written off due to project discontinuation 9.4 - - - (3,257) (4) - - (3,257) (3,257)
Other - - - (35) - (310) (345) (345)
Accumulated depreciation and amortisation
Dec 31 2016
  - - - 460,959 826,961 292,927 1,580,847 1,580,847
Impairment losses
Jan 1 2016
  - 1,452,412 1,452,412 - 40,627 194,298 234,925 1,687,337
Recognised 9.4 - - - - - 12,437 (7) 12,437 12,437
Exchange differences on translating foreign operations - 127,341 127,341 - 3,874 7,462 11,336 138,677
Used/Reversed 9.4 - - - - (4,357) (6) (7,492) (8) (11,849) (11,849)
Impairment losses
Dec 31 2016
  - 1,579,753 1,579,753 - 40,144 206,705 246,849 1,826,602
                   
Net carrying amount
Dec 31 2016
  - 12,390 12,390 1,189,487 736,267 160,126 2,085,880 2,098,270

(1) Expenditure on the YME field.
(2) Expenditure on the development of the B-8 field (PLN 212,412 thousand) and the B-3 field (PLN 771 thousand).
(3) Offshore gas pipeline from the B-3 field.
(4) Expenditure associated to the Piła area (no effect on the LOTOS Group’s profit/(loss)).
(5) Expenditure on Sleipner assets (PLN 42,495 thousand ) and Heimdal assets (PLN 3,565 thousand ).
(6) Expenditure on Heimdal assets.
(7) Production infrastructure on the Auksoras, Vėžaičiai, Kretinga, Ablinga and Ližiai fields.
(8) Girkaliai field.

 Note Non-current development assets   Non-current production assets    Total 
Poland Norway Total Poland Norway Lithuania Total
Gross carrying amount
Jan 1 2015
  578,046 1,535,085 2,113,131 512,840 582,851 628,336 1,724,027 3,837,158
Purchase 304,332 (1) - 304,332 2,194 3,903 8,290 14,387 318,719
Acquisition of Sleipner assets - - - - 394,956 (5) - 394,956 394,956
Exchange differences on translating foreign operations - (84,158) (84,158) - (87,469) 48 (87,421) (171,579)
Recognition of assets related to future costs of decommissioning of oil and gas extraction facilities - - - - 605,423 (4) - 605,423 605,423
Estimated costs of decommissioning of oil and gas extraction facilities 10,054 1,485 11,539 (304) 5,480 (250) 4,926 16,465
Reclassification to development assets 30,857 (2) - 30,857 - - - - 30,857
Reclassification of development assets to production assets (865,348) (3) - (865,348) 865,348 (3) - - 865,348 -
Reclassification to non-current assets (or disposal groups) held for sale (45,011) (4) - (45,011) - - - - (45,011)
Reversal of assets related to decommissioning of oil and gas extraction facilities 26.1 (2,750) - (2,750) - - - - (2,750)
Other (10,180) - (10,180) 4,599 (7,941) (286) (3,628) (13,808)
Gross carrying amount
Dec 31 2015
  - 1,452,412 1,452,412 1,384,677 1,497,203 636,138 3,518,018 4,970,430
Accumulated depreciation and amortisation
Jan 1 2015
  55,696 - 55,696 317,301 199,741 220,384 737,426 793,122
Depreciation and amortisation 2,427 - 2,427 23,104 129,831 37,320 190,255 192,682
Exchange differences on translating foreign operations - - - - (19,307) 645 (18,662) (18,662)
Reclassification of development assets to production assets (58,123) (3) - (58,123) 58,123 (3) - - 58,123 -
Other - - - (144) - (286) (430) (430)
Accumulated depreciation and amortisation
Dec 31 2015
  - - - 398,384 310,265 258,063 966,712 966,712
Impairment losses
Jan 1 2015
  - 1,535,085 1,535,085 - 43,415 134,509 177,924 1,713,009
Recognised 9.4 - 1,485 1,485 - - 58,733 (6)  58,733 60,218
Exchange differences on translating foreign operations - (84,158) (84,158) - (2,786) 1,056 (1,730) (85,888)
Used/Reversed - - - - (2) - (2) (2)
Impairment losses
Dec 31 2015
  - 1,452,412 1,452,412 - 40,627 194,298 234,925 1,687,337
                   
Net carrying amount
Dec 31 2015
  - - - 986,293 1,146,311 183,777 2,316,381 2,316,381

(1) Expenditure on the B-8 field (platform conversion, modifications to the transmission infrastructure and water injection wells).
(2) Related to prepayments for capital expenditure on the development of the B-8 field.
(3) Reclassification of expenditure following production launch in the B-8 field.
(4) As a result of the change of the technical concept for the project to convert the Petrobaltic rig into a production centre in the B-8 field, the Group reclassified the field development assets related to the project to assets held for sale (see Note 17). The assets represented expenditure incurred by LOTOS Petrobaltic S.A. on elements of the tubular legs of the rig, for which an impairment loss of PLN 36,634 thousand was recognised (see Note 9.4) and which were recognised as non-current assets (or disposal groups) held for sale valued at PLN 8,377 thousand, the value being − in the Management Board’s opinion − the net realisable value of the tubular legs (based on an analysis of current steel prices in Poland and on foreign markets, made by LOTOS Petrobaltic S.A.).
(5) Acquisition of Sleipner assets in Norway (for more information on the transaction, see Note 13.1.3. to the Consolidated financial statements for 2015 ).
(6) Assets related to the Kretinga, Nausodis, Girkalai, Vezaiciai, Ližiai and Ablinnga fields.


Impairment testing of assets in the B-8 field in the Baltic Sea

As at December 31st 2016 and December 31st 2015, the Group performed impairment tests for production assets related to the B-8 field.

Key assumptions underlying computation of the recoverable amount of the tested assets: 

  • the cash flow projection period was assumed to equal the asset’s planned life, 
  • the discount rate was assumed to equal the weighted average cost of capital, and was calculated at 10.07% (2015: 9.70) after taxation with the 19% marginal tax rate, 
  • production volumes were assumed to be in line with a competent person report prepared by Miller & Lents based on available current geological information, 
  • sales volumes, capital expenditure, operating expenses and field decommissioning costs were assumed in line with current projections for the B-8 field.

The following price assumptions were adopted for the estimates as part of the impairment test as at December 31st 2016: 

- for crude oil in USD/bbl (per barrel of oil equivalent)

  • 2017–2022 – prices in line with the price assumptions for the available market scenarios, 
  • 2023 and beyond − prices remaining stable in the long term on par with the 2022 level, adjusted for inflation.

The following assumptions were adopted for the estimates as part of the impairment test as at December 31st 2015:

- for crude oil in USD/bbl (per barrel of oil equivalent):

  • 2016–2019 – prices in line with the price assumptions for the available market scenarios, 
  • 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation. 


The impairment test of the B-8 field’s development assets indicated no need to recognise impairment losses on the assets.

Due to significant market volatility, in particular with respect to crude oil prices, the adopted assumptions may be subject to justifiable changes, and such changes may necessitate a revision of the carrying amounts of the field’s assets in the future. Therefore, the Group points to a number of uncertainties as to the recoverable amount of the assets:

  • volatility of market prices of crude oil,
  • estimates of investment expenditure related to contracts for which no contractor has yet been selected,
  • amount of reclamation commitments,
  • volatility of the PLN/USD exchange rate,
  • discount rates.

To determine the effect of key factors on the test results, the Group carried out an analysis of sensitivity to a -15%/+15% change in oil and gas prices, -15%/+15% change in production volumes, -15%/+15% change in the USD/PLN exchange rate, and -0.5%/+0.5% change in the discount rate. 

It was shown that the changes in the key assumptions had no effect on the impairment losses on the B-8 field’s assets.

Progress of the YME field development project in Norway

Due to significant delays in the implementation of the YME project, cost overruns, and defects of the MOPU (Mobile Offshore Production Unit) to be used in production operations in the field, in previous years the Group recognised impairment losses on the YME assets until they were fully written off in 2014.

On August 22nd 2016, the YME project partners completed activities to remove the defective MOPU from the field, financed with funds raised by the consortium members (the Group has a 20% interest in the project) under an agreement with the supplier of the MOPU (see Note 26.1). The amount of expected further costs related to the arrangement (most of which have been already contracted) was reflected in these financial statements by updating relevant provisions in accordance with the best current knowledge of the Management Board as at the date of these statements (see Note 26.1).

On December 12th 2016, the consortium partners approved a resolution to proceed with work on further development of the field and preparation of the Front-End Engineering Design with a view to drafting a revised field development plan. The revised development plan is to be approved by the Norwegian authorities by the end of 2017.

Given the nature of the Joint Operating Agreement between the YME project partners, and in connection with the guarantees issued by LOTOS Petrobaltic S.A. for the benefit of the Norwegian government with respect to LOTOS E&P Norge AS’s exploration and production activities on the Norwegian Continental Shelf, the Group takes into account that it may have to incur further capital expenditure on the YME field and to revalue the expected decommissioning costs, in particular once the revised field development plan is prepared, the YME field decommissioning concept is selected, and the Norwegian authorities approve the adopted plans. The initial assumption is that after production is launched on the basis of the revised field development plan in 2019, decommissioning of the YME project will take place in 2028−2032.

In the opinion of LOTOS E&P Norge AS, the amount of the provision for decommissioning of the YME field infrastructure (see Note 26.1) reflects the necessary commitment by the Group if the scenario of complete decommissioning materialises by 2032. This is a consequence of the phase (currently under way) of preparation of the revised field development plan and the YME field infrastructure decommissioning plan, which were adopted by the consortium with the votes of the majority of its members and reflected in the project budget, taking into account a reduction in the decommissioning cost estimate for 2028−2032. The cost estimate was reduced by an amount corresponding to a portion of the conditional budget in connection with a drop in the market cost of related services in Norway following the decline in market prices of hydrocarbons and no forecasts of a possible material change in their levels in the period covered by the analysis.

Considering the recognised impairment losses on the YME expenditure and the incurred tax losses that may be carried forward, the Group recognised a deferred tax asset in the consolidated statement of financial position as at December 31st 2016. The total amount of the tax assets related to the Group’s operations in Norway was PLN 523m as at December 31st 2016. Given that under the Norwegian tax legislation tax losses can be carried forward indefinitely, and that the Group is generating revenue from operations in the producing Sleipner gas field and the offshore gas and condensate production facility in the Heimdal field, the Management Board believes that the deferred tax assets recognised as at December 31st 2016 are fully realisable in the amount disclosed in these consolidated financial statements.

Impairment testing of the production assets of the offshore gas and condensate production facility in the Heimdal field and of the Sleipner gas field in Norway 

As at December 31st 2016, the Group tested for impairment the production assets of each centre generating cash flows from producing Heimdal and Sleipner fields. As at December 31st 2015, the Group performed impairment tests for the Heimdal fields. Their results indicated no necessity to recognise impairment losses on those assets either.

As part of impairment testing of the Norwegian production assets, their recoverable amount was determined at their fair value estimated using the discounted future cash flows method.

Key assumptions underlying computation of the recoverable amount of the tested assets:

  • the cash flow projection period was assumed to equal the asset’s planned life, 
  • the discount rate was assumed to equal the weighted average cost of capital, and was calculated at 7.63% (2015: 7.33%) after taxation with the 78% marginal tax rate (applicable in Norway), 
  • production and sales volumes, capital expenditure, operating expenses and field decommissioning costs were assumed as projected by the field operators.

The following price assumptions were adopted for the purposes of the impairment tests as at December 31st 2016: 

- for crude oil in USD/bbl (per barrel):

  • 2017–2019 – prices in line with the price assumptions for the available market scenarios, 
  • 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation, 

- for natural gas in p/th (pence/thermal units):

  • 2017–2019 − prices in line with the price assumptions for the available market scenarios, and in 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation. 

The following assumptions were adopted for the estimates as part of the impairment tests as at December 31st 2015:

- for crude oil in USD/bbl (per barrel):

  • 2016–2019 – prices in line with the price assumptions for the available market scenarios, 
  • 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation,

- for natural gas in p/th (pence/thermal units):

  • 2016–2019 − prices in line with the price assumptions for the available market scenarios, and in 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation.

The USD/NOK exchange rate used for the purposes of the impairment tests is a cross rate calculated based on forward curves for the EUR/USD and EUR/NOK currency pairs.

Due to significant market volatility, in particular with respect to oil and gas prices, the adopted assumptions may be subject to justifiable changes, and such changes may necessitate a revision of the carrying amounts of the LOTOS E&P Norge’s assets in the future.

To determine the effect of key factors on the test results, the Group carried out an analysis of sensitivity to a -15%/+15% change in oil and gas prices, -15%/+15% change in production volumes, and -15%/+15% change in the USD/NOK exchange rate.

The table below presents the estimated changes in potential impairment losses on the tested Heimdal and Sleipner assets following changes in the key assumptions:

 Factor  Change Impact on impairment losses PLN '000 
Crude oil and gas prices +/- 15% 22,626 - 14,858
Production volume +/- 15% 22,009 - 13,806
USD/NOK exchange rate +/- 15% 22,549 - 14,729
Discount rate +/- 0,5 pp - 12,895
Impairment testing of onshore oil and gas extraction facilities in Lithuania

As a result of impairment tests performed for the resources and production infrastructure in Lithuania, as at December 31st 2016 the Group recognised an impairment loss of PLN 119 thousand on production assets associated with the Kretinga field, and an impairment loss of PLN 12,318 thousand on property, plant and equipment comprising production infrastructure associated with the Auksoras, Vėžaičiai, Kretinga, Ablinga and Ližiai fields; see Note 9.4.

Following impairment tests as at December 31st 2015 an impairment loss totalling PLN 52,419 thousand was recognised on production assets associated with the Kretinga, Nausodis, Girkalai, Vėžaičiai and Ližiai fields; another impairment loss, of PLN 6,314 thousand, was recognised on the property, plant and equipment comprising production infrastructure of the Ablinga and Ližiai fields; see Note 9.4.

The Group determines the recoverable amount of the tested assets as their value in use measured using the discounted future cash flows method.

Key assumptions underlying computation of the recoverable amount of the tested assets in Lithuania:

  • the cash flow projection period was assumed to equal the asset’s planned life,
  • the discount rate was assumed to equal the weighted average cost, at 9.0% (2015: 10.1%),
  • production volumes were assumed to be in line with a competent person report prepared by Miller & Lents based on available current geological information,
  • capital expenditure was assumed to match the projected production volumes.

The following crude oil price assumptions (USD/bbl) were adopted for the purposes of the estimates made in 2016:

  • 2017–2022 – prices in line with the price assumptions for the available market scenarios,
  • 2023 and beyond − prices remaining stable in the long term on par with the 2022 level, adjusted for inflation.

Crude oil price assumptions (USD/bbl) adopted for the purposes of the estimates as at December 31st 2015:

  • 2016–2019 – prices in line with the price assumptions for the available market scenarios,
  • 2020 and beyond − prices remaining stable in the long term on par with the 2019 level, adjusted for inflation.

Due to significant market volatility, in particular with respect to crude oil prices, the adopted assumptions may be subject to justifiable changes, and such changes may necessitate a revision of the carrying amounts of the assets in the future.

To determine the effect of key factors on the test results, the Group carried out an analysis of sensitivity to a -15%/+15% change in oil prices, -15%/+15% change in production volumes, -15%/+15% change in the USD/EUR exchange rate, and -0.5%/+0.5% change in the discount rate.

The table below presents the estimated changes in impairment losses on the Lithuanian assets referred to above following changes in the key assumptions:

 Factor  Change Impact on impairment losses PLN '000 
Crude oil and gas prices +/- 15% 28,796 -41,861
Production volume +/- 15% 22,631 -33,810
USD/EUR exchange rate +/- 15% 17,532 -30,960
Discount rate +/- 0,5 pp -7 601 -

Assets related to future costs of decommissioning of oil and gas extraction facilities 

As part of its development and production assets, the Group discloses assets related to future costs of decommissioning of oil and gas extraction facilities depreciated with the units-of-production method. These assets are recognised along with the recognition and remeasurement of provisions for decommissioning of oil and gas extraction facilities.

Development assets    Production assets    Total 
Poland Norway  Total Poland  Norway Lithuania Total
Gross carrying amount
Jan 1 2016
- 122,783 122,783 108,129 829,806 2,042 939,977 1,062,760
Estimated costs of decommissioning of oil and gas extraction facilities - - - (2,921) (87,911) (389) (91,221) (91,221)
Exchange differences on translating foreign operations - 12,109 12,109 - 79,179 73 79,252 91,361
Reclassification to production assets - - - 2,223 (1) - - 2,223 2,223
Gross carrying amount
Dec 31 2016
- 134,892 134,892 107,431 821,074 1,726 930,231 1,065,123
Accumulated depreciation and amortisation
Jan 1 2016
- - - 76,568 124,010 1,341 201,919 201,919
Depreciation and amortisation - - - 1,339 261,606 185 263,130 263,130
Exchange differences on translating foreign operations - - - - 20,148 53 20,201 20,201
Reclassification to production assets - - - 2,223 (1) - - 2,223 2,223
Accumulated depreciation and amortisation
Dec 31 2016
- - - 80,130 405,764 1,579 487,473 487,473
Impairment losses
Jan 1 2016
- 122,783 122,783 - 32,029 - 32,029 154,812
Recognised - - - - - - - -
Exchange differences on translating foreign operations - 12,109 12,109 - 3,100 - 3,100 15,209
Used/Reversed - - - - (1,950) - (1,950) (1,950)
Impairment losses
Dec 31 2016
- 134,892 134,892 - 33,179 - 33,179 168,071
                 
Net carrying amount
Dec 31 2016
- - - 27,301 382,131 147 409,579 409,579

(1) Offshore gas pipeline from the B-3 field.

 Development assets Production assets  Total 
Poland Norway Total Poland  Norway Lithuania Total
Gross carrying amount
Jan 1 2015
28,571 129,699 158,270 72,558 266,534 2,298 341,390 499,660
Recognised - - - - 605,423 (2) - 605,423 605,423
Estimated costs of decommissioning of oil and gas extraction facilities 10,054 1,485 11,539 (304) 5,480 (250) 4,926 16,465
Exchange differences on translating foreign operations - (8,401) (8,401) - (47,631) (6) (47,637) (56,038)
Reversal of assets related to decommissioning of oil and gas extraction facilities (2,750) - (2,750) - - - - (2,750)
Reclassification of development assets to production assets (35,875) (1) - (35,875) 35,875 (1) - - 35,875 -
Gross carrying amount
Dec 31 2015
- 122,783 122,783 108,129 829,806 2,042 939,977 1,062,760
Accumulated depreciation and amortisation
Jan 1 2015
3,998 - 3,998 72,217 90,069 942 163,228 167,226
Depreciation and amortisation 316 - 316 37 41,810 393 42,240 42,556
Exchange differences on translating foreign operations - - - - (7,869) 6 (7,863) (7,863)
Reclassification of development assets to production assets (4,314) (1) - (4,314) 4,314 (1) - - 4,314 -
Accumulated depreciation and amortisation
Dec 31 2015
- - - 76,568 124,010 1,341 201,919 201,919
Impairment losses
Jan 1 2015
- 129,699 129,699 - - - - 129,699
Recognised - 1,485 1,485 - - - - 1,485
Exchange differences on translating foreign operations - (8,401) (8,401) - (1,684) - (1,684) (10,085)
Used/Reversed - - - - 33,713 - 33,713 33,713
Impairment losses
Dec 31 2015
- 122,783 122,783 - 32,029 - 32,029 154,812
                 
Net carrying amount
Dec 31 2015
- - - 31,561 673,767 701 706,029 706,029

(1) Reclassification of expenditure following production launch in the B-8 field.
(2) Acquisition of Sleipner assets in Norway (for more information on the transaction, see Note 13.1.3. to the Consolidated financial statements for 2015 ).

13.2.3 Other non-current assets of the upstream segment
Land Buildings, structures Plant and equipment Vehicles, other Property, plant and equipment under construction Intangible assets Total
Gross carrying amount
Jan 1 2016
11,417 96,386 84,614 539,132 15,072 29,495 776,116
Purchase - - 255 11,644 12,295 187 24,381
Transfer from property, plant and equipment under construction - - 136 10,604 (10,740) - -
Exchange differences on translating foreign operations - 66 775 12,806 29 1,721 15,397
Reclassification of refining and other assets to production assets - (42,408) (1) (16,141) (1) - - - (58,549)
Disposal - (13) (461) (13,772) - (269) (14,515)
Other - (885) (33) - (1,381) (2) (2,301)
Gross carrying amount
Dec 31 2016
11,417 53,146 69,145 560,414 15,275 31,132 740,529
Accumulated depreciation and amortisation
Jan 1 2016
3,863 34,391 45,535 235,098 - 16,650 335,537
Depreciation and amortisation 277 2,291 4,012 33,698 - 4,421 44,699
Exchange differences on translating foreign operations - 16 555 11,209 - 886 12,666
Reclassification of refining and other assets to production assets - (16,464) (1) (10,597) (1) - - - (27,061)
Disposal - (12) (356) (7,235) - (269) (7,872)
Other - (152) (3) - - (2) (157)
Accumulated depreciation and amortisation
Dec 31 2016
4,140 20,070 39,146 272,770 - 21,686 357,812
Impairment losses
Jan 1 2016
- - 562 5,343 120 - 6,025
Recognised 4 21 12 5,374 (2) - - 5,411
Exchange differences on translating foreign operations - - 19 277 9 - 305
Used/Reversed - - - (5,875) - - (5,875)
Impairment losses
Dec 31 2016
4 21 593 5,119 129 - 5,866
               
Net carrying amount
Dec 31 2016
7,273 33,055 29,406 282,525 15,146 9,446 376,851

(1) Offshore gas pipeline from the B-3 field.
(2) Including ships valued at PLN 5,333 thousand, see Note 9.4.

Land Buildings, structures Plant and equipment Vehicles, other Property, plant and equipment under construction Intangible assets Total
Gross carrying amount
Jan 1 2015
11,417 98,072 79,528 493,182 108,236 30,542 820,977
Purchase - - 1,287 252 30,466 136 32,141
Transfer from property, plant and equipment under construction - 407 3,010 29,026 (32,443) - -
Exchange differences on translating foreign operations - 2 987 17,178 93 (1,158) 17,102
Estimated costs of decommissioning, land reclamation and clean-up - (2,095) (142) - - - (2,237)
Reclassification to development assets - - - - (30,857) (1) - (30,857)
Reclassification to exploration and evaluation assets - - - - (60,577) (2) - (60,577)
Disposal - - (43) (506) - (22) (571)
Other - - (13) - 154 (3) 138
Gross carrying amount
Dec 31 2015
11,417 96,386 84,614 539,132 15,072 29,495 776,116
Accumulated depreciation and amortisation
Jan 1 2015
3,586 29,375 40,114 182,528 - 12,584 268,187
Depreciation and amortisation 277 5,014 4,764 38,991 - 4,575 53,621
Exchange differences on translating foreign operations - 2 707 14,080 - (485) 14,304
Disposal - - (37) (501) - (21) (559)
Other - - (13) - - (3) (16)
Accumulated depreciation and amortisation
Dec 31 2015
3,863 34,391 45,535 235,098 - 16,650 335,537
Impairment losses
Jan 1 2015
- - 300 1,098 - - 1,398
Recognised - - 255 (3) 4,127 (3) 117 (3) - 4,499
Exchange differences on translating foreign operations - - 7 118 3 - 128
Used/Reversed - - - - - - -
Impairment losses
Dec 31 2015
- - 562 5,343 120 - 6,025
               
Net carrying amount
Dec 31 2015
7,554 61,995 38,517 298,691 14,952 12,845 434,554

(1) Related to prepayments for capital expenditure on the development of the B-8 field.
(2) Related to operations on the Gaz Południe, Gotlandia, Łeba and Rozewie licence areas, which will be continued in 2016 in line with the upstream segment management’s decision. Applications were filed to convert the Łeba and Rozewie licences into combined oil and gas exploration, appraisal and production licences.
(3) Ships.

Other property, plant and equipment and intangible assets of the upstream segment include ships and a multi-purpose mobile drilling rig.

13.3 Other information on property, plant and equipment and intangible assets

    Property, plant and equipment used under finance lease
Dec 31 2016 Dec 31 2015
Gross carrying amount 312,277 334,209
Accumulated depreciation and amortisation 103,644 93,403
Impairment losses 800 -
Net carrying amount 207,833 240,806

The Group uses finance leases to finance primarily rolling stock assets (downstream segment); see also Note 23.4.

Allocation of depreciation and amortisation 2016 2015
Cost of sales 936,303 611,832
Distribution costs 87,474 68,769
Administrative expenses 35,628 38,722
Change in products and adjustments to cost of sales 8,489 (4,755)
Total 1,067,894 714,568

In 2016, the Group capitalised finance costs of PLN 4,840 thousand as property, plant and equipment under construction and intangible assets under development (2015: PLN 1,383 thousand) (see Note 13.1.1 and 13.1.3). As at December 31st 2016, financing costs capitalised as property, plant and equipment under construction and intangible assets under development totalled PLN 13,084 thousand (December 31st 2015: PLN 5,164 thousand). 

As at December 31st 2016, property, plant and equipment and intangible assets serving as collateral for the Group’s liabilities were PLN 6,232,650 thousand (December 31st 2015: PLN 6,538,480 thousand).

As at December 31st 2016, the Group’s future contractual commitments for expenditure on property, plant and equipment and intangible assets not disclosed in the statement of financial position amounted to PLN 1,366,651 thousand and were chiefly related to the construction of the delayed coking unit (DCU) (the EFRA Project), development of the B-8 field (B8 Project), construction of a hydrogen recovery unit (HRU) at the refinery, and expansion of the service station chain (December 31st 2015: PLN 1,773,814 thousand).

We invite you to participate in our Report's survey
Let's go Not now